PMP考試每天一練-2019年PMP考試試題118
PMP考試試題一: A project manager plans to acquire resources to execute project tasks. Contracts with vendors are evaluated to minimize the occurrence of identified risks. What process is being implemented? A. Conduct Procurements B. Make-or-Buy Analysis C. Requirements Documentation D. Plan Procurement Management 項目經理計劃獲得資源來執行項目任務。評估與供應商簽訂的合同,盡量減少發生已識別風險的可能性,這正在執行哪個過程? A.實施采購 B.自制或外購分析 C.需求文檔 D.制定采購管理計劃 PMP答案解析:評估與供應商簽訂的合同,盡量減少發生已識別風險的可能性,可以理解為采購管理計劃中的擬采用的合同類型、風險管理事項、如何識別保險合同的需求以減輕某些項目風險。 PMP參考答案:D PMP考試試題二 The project manager learns that a change request is approved. This change impacts the project cost and schedule.What should the project manager do? A.Change the baseline B.Change the risk register C.Change the work breakdown structure D.Change the resource plan 項目經理了解到一項變更請求已獲批準。這項變更將影響到項目成本和項目進度。項目經理應該怎么做? A.變更基準 B.變更風險登記冊 C.變更工作分解結構 D.變更資源計劃 PMP答案解析:變更請求獲得批準后,應該更新項目管理計劃 /基準/文件。 PMP參考答案:A |