PMP考試每天一練-2019年PMP考試試題121
PMP考試試題一: After evaluating sellers' proposals, a project manager discovers a significant variance among their prices. This makes it difficult to compare the bids and make a decision. To determine the cause of the inconsistencies, what should the project manager do? A. Hold a bidder conference. B. Review the procurement statement of work (SOW). C. Report the differences to their manager. D. Review the project SOW. 評估賣方建議書后,項目經理發現他們的價格存在顯著差異。這使得難以比較報價和做出決定。若要確定導致不一致的原因,項目經理應該怎么做? A.舉行投標人會議。 B.審查采購工作說明書(SOW)。 C.將差異報告給他們的經理。 D.審查項目工作說明書。 PMP答案解析:采購SOW應該詳細描述擬采購的產品、服務或成果,以便潛在的賣方確定他們是否有能力提供這些產品、服務或成果;如果出現明顯的報價差異,需要審查是否 SOW的描述不準確。 PMP參考答案:B PMP考試試題二 A project sponsor asks a project team to execute a project's scope in a single phase. Which of the following should be presented to the project sponsor so that a multi-phased approach can be Used? A. Stakeholder analysis B. Requirements management plan C. High-level risks D. Flowchart 項目發起人要求項目團隊在一個單獨階段執行項目范圍。應向項目發起人提交下列哪一項才能使用多階段方法? A.干系人分析 B.需求管理計劃 C.高層次風險 D.流程圖 PMP答案解析:階段與階段間的關系對如何管理需求有很大影響。項目經理為項目選擇最有效的階段間關系,并將它記錄在需求管理計劃中。 PMP參考答案:B |