PMP考試每天一練-2019年PMP考試試題129
PMP考試試題一: A program manager and a resource manager disagree regarding resource assignments across project within a program. The resource manager oversees the team members’ assignments.What structure type has been defined? A.Projectized B.Weak matrix C.Strong matrix D.functional 項目集經理和資源經理對一個項目集中的項目資源分配意見不一致。資源經理監管團隊成員的任務。這定義了那種結構類型? A.項目性 B.弱矩陣型 C.強矩陣型 D.職能型 PMP答案解析:資源經理就是職能經理,權力比較大。 PMP參考答案:B PMP考試試題二 Upon reaching the end of a project phase, a project manager learns that a functional manager is concerned about the project's implementation. What is the first action that the project manager should take to address this concern? A. Complete the project phase as planned and later meet with the functional manager to address the conern. B. Document the concern in the risk register and assess its possible impact. the project C. Identify the functional manager's specific concern D. Review organizational process assets to determine the appropriate course of action 接近項目階段結束時,項目經理發現職能經理對項目的實施情況非常擔心。若要解決這個問題,項目經理首先應該采取的措施是什么? A.按計劃完成項目階段,并在后期與職能經理開會解決這個問題 B.在風險登記冊中記錄這個問題,并評估其對項目的可能影響 C.確定職能經理具體擔心的問題 D.審查組織過程資產,確定相應的行動措施 PMP答案解析:首先確定職能經理擔心的是什么問題。 PMP參考答案:C |