PMP考試每天一練-2019年PMP考試試題132
|
PMP考試試題一: After a natural disaster occurs, the project manager discovers that a critical external resource will be delayed and will cause the team to miss a deadline. What should the project manager do next? A.Consult the communications management plan B.Refer to the procurement management plan C.Adjust the project buffer to extend the deadline D.Obtain the resource from another vendor 在發生自然災害后,項目經理發現一個關鍵外部資源將延遲,并將導致團隊延誤一個交付成果。項目經理下一步該怎么做? A.資源溝通管理計劃 B.參考采購管理計劃 C.調整項目緩沖時間延長交付期限 D.從同一個供應商獲得資源 PMP答案解析:項目經理識別了一個采購過程中的風險,應該參考采購管理計劃中的風險管理事項。 PMP參考答案:B PMP考試試題二 A customer does not approve a project deliverable. The reason is documented and the project manager is asked to repair the defect.what should the project manager do first? A. Prepare a change request B. Update the project management plan C. Understand the reason for non-acceptance D. Implement the perform quality assurance process 客戶沒有驗收某個項目可交付成果。原因已記錄在文件上,并要求項目經理修補缺陷。項目經理首先應該做什么? A.準備變更請求 B.更新項目管理計劃 C.了解沒有驗收的原因 D.執行實施質量保證過程 PMP答案解析:缺陷補救是一種變更請求。 PMP參考答案:A |