PMP考試每天一練-2019年PMP考試試題135
PMP考試試題一: Two project team members consistently disagree and criticize each other during team meetings, which negatively affects the team. What should the project manager do? A. Meet with these team members to help them find common ground. B. Take no action, since this is not affecting the project's cost or schedule. C. Initiate a team-building exercise for the project team. D. Reassign one of these team members to another project. 兩名項目組成員一直持有不同意見,并在團隊會議上批評對方,對團隊產生負面影響。項目經理應該怎么做? A.與這兩名團隊成員開會,幫助他們找到共同點。 B.不采取任何行動,因為這是不影響項目的成本或進度。 C.為項目團隊發起一項團隊建設練習。 D. 將其中一名團隊成員重新分配到另一個項目 PMP答案解析:四個選項中A為最優選項。 PMP參考答案:A PMP考試試題二 During a new system deployment, a company plans quality management. Which of the following quality control activities should be included in this process? A. Audit the technical requirements for the system's specifications B. Perform a process analysis to identify issues and plan preventive actions C. Produce a checklist to verify that a set of required steps were performed D. Examine whether the team is using best practices throughout the project 在一個新系統部署期間,公司制定質量管理計劃,下列哪一個質量控制活動應包含在這個過程中? A.審計系統技術規范的技術要求 B.執行過程分析,識別問題并計劃預防措施 C.制作一份核對表,核實已執行一系列必要的措施 D.檢查團隊在項目過程中是否使用最佳實踐 PMP答案解析:A是質量控制,BCD都是質量保證。 PMP參考答案:A |