PMP考試試題一: A 36-mile road construction project with a US$60 million budget must be completed within 24 months. At the end of the eighth month, US$25 million was spent and nine miles were completed. The project sponsor requests a status report, including earned value (EV).What is the project's EV at the end of the eighth month? A. US$15 million B. US$20 million C. US$32 million D. US$35 million 一條長約36英里的公路施工項(xiàng)目預(yù)算為6000萬美元,必須在24個月內(nèi)完成。在第八個月結(jié)束時,已經(jīng)花了2500萬美元,并完成了9英里。項(xiàng)目發(fā)起人請求提交一份狀態(tài)報告,包括掙值(EV)。那么在第八個月結(jié)束時項(xiàng)目的EV是多少? A.1500萬美元 B.2000萬美元 C.3200萬美元 D.3500萬美元 PMP答案解析:EV=實(shí)際工作量*計劃單價(6000/36 * 9) PMP參考答案:A PMP考試試題二 In a weak matrix organization, who manages the budget for a construction project where multiple change orders will be expected? A.Contractor B.Project management office C.Functional manager D.Project manager 在一個弱矩陣組織中,誰負(fù)責(zé)管理預(yù)期將有多個變更單的施工項(xiàng)目預(yù)算? A.承包商 B.項(xiàng)目管理辦公室 C.職能經(jīng)理 D.項(xiàng)目經(jīng)理 PMP答案解析:弱矩陣組織中,職能經(jīng)理負(fù)責(zé)預(yù)算,項(xiàng)目經(jīng)理很少或沒有權(quán)力。 PMP參考答案:C |