PMP考試每天一練-2019年P(guān)MP考試試題148
PMP考試試題一: The project manager identified multiple problems which have negative impact on a strategic project goal. What should the project manage do next? A.Prioritize the problems according to the influence on project objectives B.Hold a special project meeting to assign the issue to team members C.Get the approval of project sponsor to change the project objectives D.Use project contingence reserve to assign additional resource to solve the problem 項(xiàng)目經(jīng)理識(shí)別出可能對(duì)一個(gè)戰(zhàn)略項(xiàng)目目標(biāo)產(chǎn)生負(fù)面影響的多個(gè)問(wèn)題。項(xiàng)目經(jīng)理下一步該怎么做? A.確保根據(jù)對(duì)項(xiàng)目目標(biāo)的影響對(duì)每個(gè)問(wèn)題賦予優(yōu)先級(jí) B.召開(kāi)一次特別項(xiàng)目會(huì)議,將問(wèn)題委派給團(tuán)隊(duì)成員 C.獲得項(xiàng)目發(fā)起人的批準(zhǔn),變更項(xiàng)目目標(biāo) D.使用項(xiàng)目應(yīng)急儲(chǔ)備,分配額外的資源解決問(wèn)題 PMP答案解析:PM識(shí)別出可能對(duì)目標(biāo)產(chǎn)生影響的多個(gè)問(wèn)題,可對(duì)多個(gè)問(wèn)題排列優(yōu)先級(jí),優(yōu)先關(guān)注重要問(wèn)題。 PMP參考答案:A PMP考試試題二 A truck carrying critical products for a project is in a traffic accident and the products are destroyed, The project manager should refer to which of the following for a contingency plan? A. Risk reassessment B. Quantitative risk analysis C. Risk register D. Contingency reserves 一輛運(yùn)送項(xiàng)目關(guān)鍵產(chǎn)品的卡車發(fā)生交通事故,產(chǎn)品被銷毀。項(xiàng)目經(jīng)理應(yīng)參閱下列哪一份文件獲得應(yīng)急計(jì)劃? A風(fēng)險(xiǎn)再評(píng)估 B.定量風(fēng)險(xiǎn)分析 C.風(fēng)險(xiǎn)登記冊(cè) D.應(yīng)急儲(chǔ)備 PMP答案解析:四個(gè)答案中,最好的選項(xiàng)為 C。應(yīng)急計(jì)劃是事先確定好的,在一定特殊條件可以啟動(dòng)的計(jì)劃。 PMP參考答案:C |