PMP考試每天一練-2019年P(guān)MP考試試題149
PMP考試試題一: A project began nine months ago and is expected to close within three months. Using the earned value management technique, the earned value/planned value ratio is greater than one.What is the project’s status? A.Over budget B.Behind schedule C.Under budget D.Ahead of schedule 項目在九個月前開始,預計將在三個月內(nèi)結(jié)束。使用掙值管理技術(shù),掙值/計劃價值比率大于1.項目目前的狀態(tài)是什么? A.超出預算 B.落后于進度 C.低于預算 D.超前于進度 PMP答案解析:SPI=EV/PV大于1,進度提前。 PMP參考答案:D PMP考試試題二 A 36-mile road construction project with a US$60 million budget must be completed within 24 months. At the end of the eighth month. US$25 million was spent and nine miles were completed. The project sponsor requests a status report, including earned value (EV).What is the project's EV at the end of the eighth month? A. US$15 million B. US$20 million C. US$32 million D. US$35 million 一條長約36英里的公路施工項目預算為6000萬美元,必須在24個月內(nèi)完成。在第八個月結(jié)束時,已經(jīng)花了2500萬美元,并完成了9英里。項目發(fā)起人請求提交一份狀態(tài)報告,包括凈值(EV)。那么在第八個月結(jié)束時項目的EV是多少? A. 1500萬美元 B. 2000萬美元 C. 3200萬美元 D. 3500萬美元 PMP答案解析:EV=9/36*6000=1500 PMP參考答案:A |