PMP考試每天一練-2019年PMP考試試題156
PMP考試試題一: Referring to the control chart, what can be concluded about this process? A.In control, despite six measurements after April diverge from the mean B.Out of control, due to the fluctuations in February and April C.Out of control, because six measurements after April diverge from the mean D.In control, because one measurements was more than three standard deviations below mean 參考控制圖,可以對這個過程得出什么結論? A.在控制中,即使四月份后六個測量值偏離平均線 B.失去控制,因為而魚粉和四月份的波動 C.失去控制,因為四月份后六個測量值偏離平均線 D.在控制中,因為一個測量值超過平均線下方的三個標準偏差 PMP答案解析:根據七點規則,四月份后只有六個點在均值的同一側。 PMP參考答案:A PMP考試試題二 During a project’s execution, the program manager advises the project manager that the project will be cancelled. What should the project manager do next? A.Reassign the resources to other projects B.Meet with the project sponsor and the program manager C.Continue the phase to completion D.Create a change request for the delivery manager 在項目執行期間,項目集經理通知項目經理項目將被取消。項目經理下一步該怎么做? A.向其他項目重新分配資源 B.與項目發起人和項目集經理開會 C.繼續階段完成 D.向交付經理創建一份變更請求 PMP答案解析:項目經理接到通知項目將被取消,應該進行項目收尾,做好經驗教訓總結。 PMP參考答案:B |