PMP考試每天一練-2019年PMP考試試題159
PMP考試試題一: A junior project team member requests approval of a purchase order an item listed in the work breakdown structure (WBS). After reviewing the project budget, the project manager realizes that the item on the purchase order is not listed in the project budget.What should be the reason for this issue? A. The scope baseline was pot used as an input during the estimate costs process B. Expert judgment was not used during the estimate cost process C. Procurement planning was not used during the estimate process D. The bottom-up estimating method was used during estimate costs process 初級項目團隊成員請求批準工作分解結構(WBS)中所列某項物品的采購訂單。審查項目預算后,項目經理發現采購訂單上的物品未列入項目預算。造成這個問題的原因是什么? A.在估算成本過程中未將范圍基準作為一項輸入 B.在估算成本過程中未使用專家判斷 C.在估算成本過程中未使用采購規劃 D.在估算成本過程中使用了自下而上估算法 PMP答案解析:估算成本時沒有參考范圍基準作為輸入。 PMP參考答案:A PMP考試試題二 1The project’s budget is US$750,000. At day 42, 40% of the project is completed, at a cost of US$500,000. After the project manager reports the cost performance index, the customer refuses to add more funds to the project.To complete the project on time and on budget, the project’s to-complete performance index must by which of the following? A.0.6 B.0.8 C.1.4 D.1.8 項目預算為750,000沒有。在第42天時,項目已完成40%,成本為500,000美元。在項目經理報告成本績效指數后,客戶拒絕為項目增加更多資金。若要按時按預算完成項目,項目的完工尚需績效指數必須為下列哪一項? A.0.6 B.0.8 C.1.4 D.1.8 PMP答案解析:D PMP參考答案:TCPI=(BAC-EV)/(BAC-AC)=(750000-0.4*750000)/(750000-500000)=1.8 |