PMP考試每天一練-2019年PMP考試試題165
PMP考試試題一: The project sponsor is concerned about several defects being reported during the quality control phase and asks the project manager to investigate the source for these defects. That tool should the project manager use to perform this task? A.Control chart B.Pareto chart C.Fishbone diagram D.inspection 項目發起人擔心在質量控制階段中報告的多個缺陷,要求項目經理調查這些缺陷的原因。項目經理應該使用什么工具來執行這項任務? A.控制圖 B.帕累托圖 C.魚骨圖 D.檢測 PMP答案解析:調查缺陷原因用魚骨圖。 PMP參考答案:C PMP考試試題二 During project closure, the project manager records information in the company’s inventory for future project knowledge. The project manager works on which of the following assets? A.Approved change requests B.Quantitative risk analysis C.Accepted deliverables D.Historical information 在項目收尾期間,項目經理更新了公司的信息庫,應用于未來項目。項目經理正從事下列哪一資產工作? A.已批準的變更請求 B.定量風險分析 C.已接受的可交付成果 D.歷史信息 PMP答案解析:PMBOK原話:把歷史信息和經驗教訓信息存入經驗教訓知識庫,供未來項目或階段使用。可包括問題與風險的信息,以及適用于未來項目的有效技術的信息。 PMP參考答案:D |