PMP考試每天一練-2019年PMP考試試題169
PMP考試試題一: A project manager meets with two team members who maintain opposing viewpoints. In the meeting, the project manager emphasizes areas of agreement and plays down differences Which conflict management technique is the project manager practicing? A.Confront B.Smooth C.Force D.collaborate 項目經理與兩名持相反觀點的團隊成員開會。會議中,項目經理強調一致而非差異。項目經理采用的是那種沖突管理技術 A.面對 B.緩解 C.強迫 D.合作 PMP答案解析:強調一致而非差異,這是求同存異。 PMP參考答案:B PMP考試試題二 Midway through the project, the project manger must determine if the planned budget will be sufficient to complete the project. Which of the following should the project manager calculation and then compare with the original budget A.Estimate to complete B.Estimate at completion C.Earned value D.Budget at completion 在項目中途,項目經理必須決定計劃預算是否足以完成該項目。項目經理應該計算下列哪一項值再與原始預算對比? A.完工尚需估算 B.完工估算 C.掙值 D.完工預算 PMP答案解析:計劃預算是BAC,需要用EAC與之對比。 PMP參考答案:B |