PMP考試每天一練-2019年PMP考試試題170
PMP考試試題一: The project team uses the following control chart monitor change requests in the project scope. According to the chart, which of the following could have been improved upon? A.Integrate change control B.Collect requirements C.Perform quality assurance D.Control scope 項目團隊使用一下控制圖來監控項目范圍中的變更請求。根據這些控制圖,可以改進下列哪一項? A.整合變更控制 B.收集需求 C.實施質量保證 D.控制范圍 PMP答案解析:三個數據點落在控制線以外,說明過程失控。監控變更請求數量的過程失控,需要加強范圍管理,控制范圍。 PMP參考答案:D PMP考試試題二 A department is planning a project for which the project manager identifies widely different stakeholder expectations, The project manager is concerned that some stakeholders will create obstacles during project implementation. What should the project manager do next? A. Improve relationships with those stakeholders liable to create obstacles, and determine where assistance may be offered. B. Report the behavior of some of the stakeholders to the project sponsor, and ask the sponsor to make considerations in advance. C. Covertly gather some evidence of the stakeholders' obstructive behavior and prepare to file a complaint, D. Update the risk register, and develop a plan to address the obstacles. 某部門要實施一個計算機系統項目,項目經理在調研中發現,不同的項目干系人對項目的期望值有很大的矛盾,項目經理擔心某些項目干系人會在項目實施過程中設置障礙。請問應該怎么處理? A.和可能設置障礙的干系人改善關系,看看是否可以在某些地方提供幫助。 B.向項目發起人匯報某些干系人的行為,請發起人提前考慮。 C.默默收集某些干系人阻礙行為的證據,作好投訴準備。 D.作為風險記錄在案,并制定好應對障礙的計劃。 PMP答案解析:推薦D答案,作為風險進行管理。 PMP參考答案:D |