PMP考試每天一練-2019年PMP考試試題176
PMP考試試題一: Since the quality of the completed project is important to the end user, the project manager outlines how to achieve a quality project to the end user. The following? A.Quality metrics B.Lessons learned from a similar project C.Quality management plan D.Communications management plan 由于已完成項目的質量對最終用戶非常重要,項目經理簡要描述如何向最終用戶完成高質量項目。項目經理應該分享下列哪一項? A.質量測試指標 B.類似項目的經驗教訓 C.質量管理計劃 D.溝通管理計劃 PMP答案解析:質量管理計劃描述將如何實施組織的質量政策,以及項目管理團隊準備如何達到項目的質量要求。 PMP參考答案:C PMP考試試題二 One project activity has a free float of two days. What statement can be made about the project? A. The total float of the project in two days. B. The project's subsequent activities can be rescheduled if the activity is delayed by two days. C. The activity can be delayed by two days without impacting subsequent activities start dates. D. The activity may be on the critical path. 一個項目活動有兩天的自由浮動時間。下列哪個說法適合這個項目? A.項目的總浮動時間為兩天 B.如果該活動延期兩天,可以對項目的后續活動重新安排進度計劃 C.該活動可以延遲兩天,而不會影響后續活動的開始日期 D.該活動可能在關鍵路徑上 PMP答案解析:自由浮動時間為自由時差,說明活動推遲2天而不會影響緊后活動的最早開始日期。 PMP參考答案:C |