PMP考試每天一練-2019年PMP考試試題178
PMP考試試題一: During a project meeting, a team member identifies and submits a risk to the project manager. After an evaluation of the risk, the project team determines the impact, probability, and a risk response.Before performing these activities, what process must be completed? A.Plan risk management B.Identify risks C.Perform quantitative risk analysis D.Plan risk response 在項目會議上,一名團隊成員識別到一個風險,并將其提交給項目經(jīng)理。在評估完風險后,項目團隊確定了影響、發(fā)生概率和風險應對措施。執(zhí)行這些活動之前,必須完成那個過程? A.制定風險管理計劃 B.識別風險 C.實施定量風險分析 D.制定風險應對計劃 PMP答案解析:在“識別風險、風險定性分析、規(guī)劃風險應對”之前,需要做的是規(guī)劃風險管理。 PMP參考答案:A PMP考試試題二 A project relies on a specialized tool to keep track of several critical path activities. The specialized tool fails, but is quicklyreplaced by a backup tool, What describes this situation? A. Exploiting an opportunity to avoid risk B. Effectively using risk avoidance C. Deploying a successful risk mitigation strategy D. Managing risk closure through risk prevention 一個項目依靠專業(yè)工具來跟蹤幾個關鍵路徑上的活動。專業(yè)工具發(fā)生故障,但很快被一個備份工具所取代。下列哪一項能夠描述這個情況? A.開拓機會,回避風險 B.有效利用風險回避措施 C.部署一個成功的風險減輕策略 D.通過風險預防管理風險關閉 PMP答案解析:是一個有效的風險減輕措施。 PMP參考答案:C |