PMP考試每天一練-2019年PMP考試試題182
PMP考試試題一: A project manager is assigned a project with a limited schedule, and realizes that the deadline is at the end of the year when most team members take their vacations. In which document would the project manager expect to find this high-level risk? A.Project charter B.Issue log C.Work breakdown structure D.Organizational process assets 項目經理被任命管理一個工期有限的項目,并意識到項目期限處于大部分團隊成員都在休假的年底。項目經理可在哪一份文件中找到該高風險? A.項目章程 B.問題日志 C.工作分解結構 D.組織過程資產 PMP答案解析:項目章程中有高層級風險(high-level risk) PMP參考答案:A PMP考試試題二 An innovative project has poorly defined product requirements. During the kick-off meeting, on what should the project manager focus? A. Conducting a requirements analysis with the stakeholders B. Agreeing on the work deliverables, schedule, resources, and costs C. Validating the project charter with the stakeholders D. Ensuring everyone is aligned with the project requirements 一個創新項目的產品需求定義很差。在項目啟動大會上,項目經理應該關注哪一點? A.與項目干系人開展需求分析 B.約定工作可交付成果、進度計劃、資源和成本 C.與項目干系人一起核實項目章程 D.確保每個人與項目需求保持一致 PMP答案解析:通過核實項目章程與干系人進行高層級共識。 PMP參考答案:C |