PMP考試每天一練-2019年P(guān)MP考試試題189
PMP考試試題一: Task A has a cost estimate of US$1,000 and scheduled completion date of December 30th, with a total duration of 10 days. The project manager reviews the task’s progress on December 27th, and it is 50% complete. The resource assigned to task A has spent US$500 to date.By adding a resource, the project manager is using which of the following? A.Budgeting B.Crashing C.Fast tracking D.Damage controlling 任務(wù)A的成本估算為1000美元,計(jì)劃完成日期是12月30日,總工期為10天。項(xiàng)目經(jīng)理在12月27日查看任務(wù)進(jìn)度發(fā)現(xiàn),任務(wù)完成50%。到目前為止分配給任務(wù)A的資源已經(jīng)花了500美元。通過增加一名資源,項(xiàng)目經(jīng)理使用的是下列哪一項(xiàng)? A.制定預(yù)算 B.趕工 C.快速跟進(jìn) D.損害控制 PMP答案解析:通過增加資源來壓縮工期 PMP參考答案:B PMP考試試題二 Project team members are participating in a work stoppage in solidarity with members of their trade union. Due to safety concerns, this action causes a three-day project delay. How should the project manager address this? A. Change the project schedule. B. Negotiate with the trade union C. Arrange a brainstorming session. D. Issue a change request. 項(xiàng)目團(tuán)隊(duì)成員正在參與停工,聲援他們的工會成員。出于安全考慮,這項(xiàng)行動導(dǎo)致項(xiàng)目延期三天。項(xiàng)目經(jīng)理應(yīng)該如何解決這個問題? A.變更項(xiàng)目進(jìn)度計(jì)劃。 B.與工會協(xié)商。 C.安排一次頭腦風(fēng)暴會議。 D.簽發(fā)變更請求。 PMP答案解析:通過變更請求來處理進(jìn)度計(jì)劃的變更。 PMP參考答案:D |