PMP考試每天一練-2020年PMP考試練習題1
PMP考試練習題一: A risk in the risk register is realized late in the project. What would be the most effective response to the situation? A. Use the management reserve. B. Perform a quantitative risk analysis. C. Perform a qualitative risk analysis. D. Use the contingency reserve. 在風險登記冊中的一個風險在項目后期發生。應對這種情況的最有效措施是什么? A.使用管理儲備。 B.執行定量風險分析。 C.執行定性風險分析 D.使用應急儲備。 PMP答案解析:對于已知風險發生使用應急儲備。 PMP參考答案:D PMP考試練習題二 A project team member's behavior is disruptive and does not comply with the company's standards. The project manager speaks with the team member, but there is no improvement ill their behavior.What should the project manager do next? A. Request that the functional manager reassign the team member B. Escalate the issue to the project sponsor C. Organize a project team meeting to reinforce the company's standards D. Request support from the human resource department 項目團隊成員的行為具有破壞性,且與公司標準不符。項目經理與團隊成員談話,但是他們的行為并無任何改進。 A.請求職能經理重新分配團隊成員 B.將該問題上報給項目發起人 C.安排項目團隊會議,強調公司標準 D.請求人力資源部門的支持 PMP答案解析:進行正式口頭溝通。 PMP參考答案:C |