PMP考試每天一練-2020年PMP考試試題9
PMP考試試題一: At the last minute, a project team implements a new feature that is not included in the scope statement. To obtain customer approval, what process should the project manager implement next? A. Plan Scope Management B. Validate Scope C. Perform Integrated Change Control D. Perform Qualitative Risk Analysis 在最后一刻,項團隊實施了范圍說明書中未包含的新功能。若要獲得客戶的批準,項目經理下一步應執行哪個過程? A.制定范圍管理計劃 B.核實范圍 C.執行整體變更控制 D.執行定性風險分析 PMP答案解析:未包含的新功能要獲得客戶的批準,首先應該進行變更,把新功能添加到范圍基準中。 PMP參考答案:C PMP考試試題二 In the project planning period, should use what technology to digital quantification risk on overall project objectives impact? A. Develop risk response plan B. Risk identification C. Quantitative risk analysis D. Qualitative risk analysis 在項目規劃期間,應使用什么技術來數字量化確定風險對總體項目目標的影響? A. 制定風險響應計劃 B. 識別風險 C. 定量風險分析 D. 定性風險分析 PMP答案解析:通過定量分析來評估對項目總體目標的影響。 PMP參考答案:C |