PMP考試每天一練-2020年PMP考試試題12
PMP考試試題一: A project manager estimates costs for a new software project. Based on past experience , the company developed a statistical relationship between the number of screens in a module and the labor hours required to produce a module.What cost estimating technique should be used to take advantage of this information? A.Analogous B.Parametric C.Bottom-up D.Rough order of magnitude 項目經理估算一個新軟件項目的成本。按照過往經驗,公司制定了模塊屏幕數量和生產一個模塊所需的勞動小時數之間的統計關系。應使用什么成本估算技術來利用這項信息? A.類比估算 B.參數估算 C.自下而上估算 D.粗略級估算 PMP答案解析:數量和以往所需小時數的統計關系,這是參數估算。 PMP參考答案:B PMP考試試題二 When preparing a business case with a financial analyst, what key document is needed? A. Cost-benefit analysis B. Statement of work C. Contract D. Project charter 在與財務分析師準備商業論證時,需要以下哪一份關鍵文件? A.成本效益分析 B.工作說明書 C.合同 D.項目章程 PMP答案解析:PMBOK69頁原話:。在商業論證中,開展業務需要和成本效益分析,論證項目的合理性,并確定項目邊界。 PMP參考答案:A |