PMP考試每天一練-2020年PMP考試試題16
PMP考試試題一: As the project experiences process failures, which method should the project manager use to identify where the concerns exist and opportunities for improvement? A.Run charting B.Affinity diagramming C.Flowcharting D.brainstorming 因為項目經歷過程失敗,項目經理應使用哪種方法來確定存在的問題以及改進機會? A.趨勢圖 B.親和圖 C.流程圖 D.頭腦風暴法 PMP答案解析:流程圖也叫過程圖,過程失敗需要使用過程圖來分析哪個環節出錯了。 PMP參考答案:C PMP考試試題二 During a project's concept, prototype, development, and testing phases, additional funding is requested several times. After the product launch, the budget is updated and the project manager determines there is a negative cost variance (CV).Which of the following does this indicate? A. Original budget is greater than the total cost at completion B. Total cost of the project is greater than the planned value (PV) C. Total incremental funding exceeded the original budget D. Earned value (EV) is greater than the actual cost (AC) 在項目的概念、原型、開發和測試階段,多次請求提供額外資金。在發布產品后更新預算,項目經理確定成本偏差(CY)為負的。這表明了下列哪一項? A.原始預算大于完工時總項目成本 B.項目總成本大于計劃價值(PV) C.總增量資金超出原始預算 D.凈值(EV)大于實際成本(AC) PMP答案解析:CV<0說明成本超支,項目總成本大于計劃價值。 PMP參考答案:B |