PMP考試每天一練-2020年PMP考試試題17
PMP考試試題一: The stakeholders request the project manager report indirect and direct costs separately. Which of the following is a direct cost? A.Telephone service costs B.Training for a duty required by the project C.Jury duty pay D.Employee salary 項目干系人要求項目經理分別報告間接成本和直接成本。以下那一項屬于直接成本? A.電話服務成本 B.項目需要的崗位培訓 C.陪審員義務支付 D.員工工資 PMP答案解析:看英文理解為此項目需要的崗位培訓。 PMP參考答案:B PMP考試試題二 Aproject manager completes development of the project management plan. Approval is obtained from all the key stakeholders, with the exception of the sates manager. Should the project manager proceed with project execution? A. No; the project manager should complete a risk register and escalate to the project sponsor. B. No; the project manager should continue to follow the process and obtain the sales manager's approval, C. Yes; the project manager should proceed and inform the project sponsor of the situation. D. Yes; the project manager should proceed to avoid delay, and follow up with the sales manager as soon as possible. 項目經理完成項目管理計劃的制定。已經獲得除銷售經理以外的所有關鍵干系人批準。項目經理是否應繼續執行項目? A.否:項目經理應完成一份風險登記冊,并上報給項目發起人。 B.否:項目經理應繼續遵循過程,并獲得銷售經理的批推。 C.是:項目經理應繼續并將情況通知項目發起人。 D.是:項冒經理應繼續,以避免延期,并盡快與銷售經理跟進。 PMP答案解析:項目管理計劃制定后應該獲得關鍵干系人的批準后才可執行。 PMP參考答案:B |