PMP考試每天一練-2020年PMP考試試題21
PMP考試試題一: Due to quality control issues, a project is behind schedule. There is no obvious pattern to the identified defects. Using a qualitative approach, which quality control tool should be used to determine the source of the defects? A. Histogram B. Pareto chart C. Scatter diagram D. Cause and effect diagram 由于質量控制問題,項目落后于進度。沒有識別缺陷的明顯模式。使用定性方法,應使用哪一種質量控制工具來確定缺陷來源? A.直方圖 B.帕累托圖 C.散點圖 D.因果圖 PMP答案解析:找原因、找缺陷來源用因果圖。 PMP參考答案:D PMP考試試題二 During project implementation, a critical item is delivered late because a customer’s safety requirement was not considered. This late delivery impacts the project team’s working hors The project manager should first identify this constraint in which of the following documents? A.Project management plan B.Resource management plan C.Risk register D.Project charter 在項目實施期間,由于未考慮客戶的安全要求,一個關鍵項延遲交付。該延遲交付影響了項目團隊的工作時間。項目經理應事先在下面那一份文件中識別該制約因素? A.項目管理計劃 B.資源管理計劃 C.風險登記冊 D.項目章程 PMP答案解析:項目章程中包含了制約因素。 PMP參考答案:D |