PMP考試每天一練-2020年PMP考試試題31
PMP考試試題一: As the project nears completion, the customer voices concerns with the quality of the product delivered. What method will identify the extent of the quality issues? A.Six sigma B.Risk audit C.Statistical sampling D.Expert judgment 隨著項目臨近完工,客戶表達了對于已交付產品質量的擔憂。用什么方法將識別質量問題的范圍? A.六西格瑪 B.風險審計 C.統計抽樣 D.專家判斷 PMP答案解析:the extent of the quality issues,質量問題的范圍、質量問題的程度。控制質量可以識別質量問題的程度,統計抽樣是控制質量的工具。 PMP參考答案:C PMP考試試題二 During a company’s relocation to a new data center, a project team member discovers that the new data center’s power supply will not be sufficient. To support forecasted growth over the next three years, additional resources costing US$480,000 will be required. As the project manager had previously identified this as a risk, what tool should have been used to determine if the contingency budget would adequately cover this costs? A. Status meeting B. Reserve analysis C. Risk reassessment D.Technical performance measurement 在公司遷址到一個新數據中心期間,一名項目團隊成員發現新數據中心的電源不足。為了支持在未來三年內的預測增長,將需要US$48萬的額外資源。由于項目經理之前已將此識別為一個風險,應使用什么工具來確定應急儲備足以涵蓋成本? A.狀態會議 B.儲備分析 C.風險再評估 D.技術績效測量 PMP答案解析:儲備分析是在項目的任何時候,比較剩余應急儲備與剩余風險量,從而確定剩余儲備是否仍然合理。 PMP參考答案:B |