PMP考試每天一練-2020年P(guān)MP考試試題35
PMP考試試題一: During the execution phase, a stakeholder asks for a change, which includes obtaining new subcontractors. The change is approved according to the change management plan and is ready to be implemented.To minimize the impact of this change, which of the following should be updated during the change approval? A.Risk urgency assessment document B.Risk register C.Procurement documentation D.Communication matrix 在階段執(zhí)行期間,干系人要求變更,變更包括獲得新的分包商。變更按照變更管理計劃批準,并準備實施。為了盡可能減少這個變更的影響,在變更批準期間應(yīng)更新下列哪一項? A.風(fēng)險緊迫性評估文件 B.風(fēng)險登記冊 C.采購文檔 D.溝通矩陣 PMP答案解析:題干的意思是要減少“換分分包商”這個變更的影響,換分包商是一個風(fēng)險,應(yīng)應(yīng)該記錄進風(fēng)險登記冊,以便后續(xù)對其進行行分析、制定應(yīng)對措施等。 PMP參考答案:B PMP考試試題二 During a meeting, a customer asks for a change in the color of the product. The project team agrees it is a minor change with no impact on cost, scope, schedule, or risk. The project manager gives verbal approval during the meeting.Which of these statements applies to this decision? A. Acceptable, provided the project sponsor approves B. Unacceptable, because all change requests must be approved by a change control board (CCB) C. Unacceptable, because a change request must be submitted in writing using a standard template D. Acceptable, provided the change is documented 在一次會議上,客戶要求改變產(chǎn)品的顏色。項目團隊同意這是有一個小變更,將不會對成本,范圍,進度或風(fēng)險產(chǎn)生影響,會議上,項目經(jīng)理給予口頭批準。下列哪一項說法適用這個決定? A.可接受,只要項目發(fā)起人批準 B.不可接受,因為所有變更請求均必須獲得變更控制委員會(CCB)的批準 C.不可接受,因為變更請求必須使用標準模版書面提交 D.可接受,只要已記錄變更情況 PMP答案解析:不會對成本、范圍、進度或風(fēng)險產(chǎn)生影響,PM可自主決策,但也要進行正式書面記錄。 PMP參考答案:D |