PMP考試每天一練-2020年PMP考試試題42
PMP考試試題一: The project is over budget, but several opportunities to reduce the project’s cost were previously identified. The project manager would like to exploit these opportunities.Which of the following should the project manger review first? A.risk register B.cost management plan C.change control system D.risk management plan 項目超出預算,但是之前已經確定出多個減低成本的機會。項目經理希望利用這些機會。項目經理應首先審查下列哪一項? A.風險登記冊 B.成本管理機會 C.變更控制系統 D.風險管理計劃 PMP答案解析:“機會”是積極的風險,風險登記冊中有風險清單和潛在的應對措施。 PMP參考答案:A PMP考試試題二 During testing of a new software program, the test team logs the number of defects found each week. The project manager reviews the data to determine if the number of defects is within the acceptable limits.What tool does the project manager use? A. Control chart B. Cause and effect diagram C. Pareto chart D. Histogram 在測試一個新的軟件項目集期間,測試團隊記錄每周發現的缺陷數量。項目經理審查數據確定缺陷數量是否處于可接受限值之內。項目經理使用的是什么工具? A.控制圖 B.因果圖 C.帕累托圖 D.直方圖 PMP答案解析:PMBOK:控制圖,可用來監測成本與進度偏差、產量、范圍變更頻率或其他管理工作成果,以便幫助確定項目管理過程是否受控。 PMP參考答案:A |