PMP考試每天一練-2020年PMP考試試題45
PMP考試試題一: A project manager obtains seller responses, as well as selects a seller to provide one of the project’s key components. The project manager completed which of the following processes? A.Control procurements B.Direct and manage project work C.Plan procurement management D.Conduct procurements 項目經理獲得供應商響應,并選擇了一名供應商提供項目的其中一個關鍵組成部分。項目經理完成的是下列哪一個過程? A.控制采購 B.指導和管理項目工作 C.規劃采購管理 D.進行采購 PMP答案解析:D的英文Conduct procurements是實施采購。實施采購是獲得賣方應答并選擇賣方。 PMP參考答案:D PMP考試試題二 To complete a product and release it as planned, the project budget must be increased significantly. The project sponsor asks for a cost estimate.Which method for cost estimation should be used? A. Earned value (EV) B. Reserve analysis C. Program evaluation and review technique (PERT) D. Parametric estimating 為完成一項產品并按計劃發布,必須增加大量項目預算。項目發起人要求執行成本估算。應使用哪種成本估算方法? A.凈值(EV) B.儲備分析 C.計劃評審技術(PERT) D.參數估算 PMP答案解析:為應對成本的不確定性,成本估算中可以包括應急儲備。隨著項目信息越來越明確,可以動用、減少或取消應急儲備。 PMP參考答案:B |