PMP考試每天一練-2020年PMP考試試題46
PMP考試試題一: A project manager prioritizes project risks based on the probability of occurrence and potential of occurrence and potential impact to the project. Which of the following is being performed? A.Quantitative risk analysis B.Qualitative risk analysis C.Schedule network analysis D.Plan risk analysis 項目經理根據發生概率以及對項目的潛在影響對項目風險排列優先順序。項目經理正在進行下列哪一項? A.定量風險分析 B.定性風險分析 C.進度網絡分析 D.計劃風險分析 PMP答案解析:對風險排列優先順序,這是在對風險進行定性分析。 PMP參考答案:B PMP考試試題二 Due to resource constraints, a project manager determines that a portion of the project work must be outsourced, Which of the following inputs are required to ensure the requirements and the timeline are met? A. Qualified sellers’ list and scope B. Schedule and scope C. Cost estimates and performance D. Cost estimates and schedule 由于資源約束條件,項目經理決定必須外包部分項目工作。為確保滿足需求和時間線,需要下列哪一項輸入? A.合格賣方清單和范圍 B.進度和范圍 C-成本估算和績效 D.成本估算和進度 PMP答案解析:規劃采購管理的輸入。 PMP參考答案:B |