PMP考試每天一練-2020年P(guān)MP考試試題50
PMP考試試題一: During the upgrade of a new telecommunications system, the project team discovers the new soft ware patches may cause instability during live operations under certain conditions. After receiving this information, the project manager prepares additional tests.What type of risk response is being performed? A.Acceptance B.Mitigation C.Avoidance D.Transfer 在升級新電信系統(tǒng)當(dāng)中,項(xiàng)目團(tuán)隊(duì)發(fā)現(xiàn)新軟件補(bǔ)丁可能在特定環(huán)境下的有效運(yùn)行期間造成不確定性,接受到這個(gè)信息后,項(xiàng)目經(jīng)理準(zhǔn)備了額外測試。這是執(zhí)行什么類型的風(fēng)險(xiǎn)應(yīng)對策略? A.接受 B.減輕 C.回避 D.轉(zhuǎn)移 PMP答案解析:擔(dān)心可能出錯(cuò),PM準(zhǔn)備了額外測試、多做了額外測試,這是減輕。 PMP參考答案:B PMP考試試題二 The project manager identifies that a finish-to-start dependency for an activity on the critical path is missing. The project schedule was already communicated to the customer. What should the project manager have done to avoid this issue? A. Reviewed the work breakdown structure B. Conducted a schedule network analysis C. Prepared a risk management plan D. Conducted an earned value analysis 項(xiàng)目經(jīng)理發(fā)現(xiàn)關(guān)鍵路徑上一項(xiàng)活動的開始到結(jié)束依賴關(guān)系遺漏了。項(xiàng)目進(jìn)度計(jì)劃已經(jīng)與客戶溝通。若要避免這個(gè)問題,項(xiàng)目經(jīng)理應(yīng)該事先做什么? A.審查工作分解結(jié)構(gòu) B.進(jìn)行進(jìn)度網(wǎng)絡(luò)分析 C.制定風(fēng)險(xiǎn)管理計(jì)劃 D.進(jìn)行掙值分析 PMP答案解析:進(jìn)行進(jìn)度網(wǎng)絡(luò)分析,分析依賴關(guān)系。 PMP參考答案:B |