PMP考試試題一: During the monitoring and controlling phase, a client requests that only eight of the 13 originally planned tests be conducted. What should the project manager do next? A.Ask the client to submit a change request B.Change the scope baseline C.Review the risk/reward clauses in the contract D.Review the penalty clauses in the contract 在監控階段,一名客戶請求只需開展13個原始計劃測試中的其中八個。項目經理下一步應該怎么做? A.讓客戶提交一份變更請求 B.變更范圍基準 C.查看合同中的風險/獎勵條款 D.查看合同中的懲罰條款 PMP答案解析:有變更,遵循變更管理流程。 PMP參考答案:A PMP考試試題二 A project’s total cost is US$200,000. The project management requests a study to verify whether the project will run behind schedule. The project has a 35% chance ofincurring a penalty of US$20,000 due to a delay in completion. There is a 65% chance that the company will earn US$500,000 on the project. What is the expected monetary value? A. US$118,000 B. US$293,000 C. US$318, 000 D. US$325,000 項目總成本為US$200,000.項目管理辦公室要求開展一項研究,來驗證項目是否會落后于進度。項目有35%的機會發生因完工延期所導致的US$20,000罰款。還有65%的機會公司將在項目中獲利US$500,000。那么預期貨幣價值是多少? A. US$118,000 B. US$293,000 C. US$318,000 D. US$325,000 PMP答案解析:EMV=35%*(-20000)+65%*500000=318000 PMP參考答案:C |