PMP考試每天一練-2020年PMP考試試題53
PMP考試試題一: During the project’s implementation phase, the project manager realizes there is a gap in the soft skills of the project team members. The project manager determines and documents the root cause.The project manager uses which of the following? A.Lessons learned B.Issue log C.Risk management plan D.Requirements traceability matrix 在項目執行階段,項目經理意識到項目團隊成員在軟技能方面存在差距。項目經理確定并記錄根本原因。項目經理使用的是下列哪一項? A.經驗教訓 B.問題日志 C.風險管理計劃 D.需求跟蹤矩陣 PMP答案解析:經驗教訓是記錄項目成功經驗與失敗的教訓。選項B:問題日志是記錄有質疑或爭議的觀點或事項,議而未決的觀點或事項,或者有對立看法或異議的觀點或事項。 PMP參考答案:A PMP考試試題二 A company wants to initiate an R&D type project and identifies a list of product features for development. The goal is to complete a prototype by the end of the financial year. Initial estimates indicate that to deliver all the features, the sponsor's budget and schedule will be exceeded.What should the project manager revise to meet the company's expectations? A. Schedule B. Functionality C. Charge-out rates D. Project charter 一家公司希望啟動一個研發項目,并確定了一份產品功能開發清單。其目標是在財政年底結束之前完成原型。初始估算表明,若要交付所有功能,將超出發起人的預算和進度計劃。項目經理應修訂哪一項來滿足公司的期望? A.進度計劃 B.功能 C.費率 D.項目章程 PMP答案解析:打算啟動一個項目,大致預算和總體進度計劃不滿足,需要修訂章程。 PMP參考答案:D |