PMP考試每天一練-2020年PMP考試試題80
PMP考試試題一: Midway through a project to upgrade a company’s system. It is determined that there is an incompatibility between the existing hardware and the newly installed equipment.What should the project manager do first? A.Identify the team member responsible for the equipment procurement error B.Perform a quantitative risk analysis C.Document, monitor, and track the issue in the issue log D.Perform a qualitative risk analysis 在一個升級公司系統的項目中途,確定現有硬件和新安裝設備之間存在一個不兼容處。項目經理首先應該做什么? A.找出負責設備采購錯誤的團隊成員 B.執行定量風險分析 C.在問題日志中記錄、監控和跟蹤問題 D.執行定性風險分析 PMP答案解析:“確定”現有硬件和新安裝設備之間存在一個不兼容處,說明不是風險,是個問題。應該在問題日志中記錄、跟蹤。 PMP參考答案:C PMP考試試題二 Each time a project component is tested, the component passes user acceptance testing and fulfills all requirements, what process did the project manager implement and execute repeatedly? A. Control Quality B. Perform Quality Assurance C. Configuration Analysis D. Sponsor Reviews 每次測試項目部件,該部件都通過用戶的驗收測試并滿足所有需求。項目經理反復實施和執行哪一個過程? A.控制質量 B.執行質量保證 C.配置分析 D.發起人審查 PMP答案解析:達到質量標準,能通過驗收測試,這是質量控制。 PMP參考答案:A |