PMP考試每天一練-2020年PMP考試練習題95
PMP考試練習題一: Project team members are located in different time zones. In this situation, which of the following becomes increasingly important to the project’s outcome? A.Communications management plan B.Risk management plan C.Stakeholder management plan D.Human resource management plan 項目團隊成員位于不同時區。在這種情況下,下列哪一項對項目成果越來越重要? A.溝通管理計劃 B.風險管理計劃 C.干系人管理計劃 D.人力資源管理計劃 PMP答案解析:位于不同時區的成員是虛擬團隊,溝通尤為重要。 PMP參考答案:A PMP考試練習題二 A project with a budget of US$800,000 is 40 percent complete and US$360,000 has already been spent.According to the actual performance and based on the cost index, what should the To-Complete Performance Index(TCPI) be to comply with the budget, and cost baseline? A. 0.89 B. 0.9 C.1.1 D. 2.19 一個預算為800,000美元的項目已完成40%, 已花費360,000美元的預算。按照實際績效并根據成本指數,若要符合預算和成本基準,完工尚需績效指數(TCPI)應為多少? A.0.89 B.0.9 C.1.1 D.2.19 PMP答案解析:( TCPI)=480000/440000=1.09 PMP參考答案:C |