PMP考試練習題一: A project has complex dependencies between activities. The activities are assigned to resources in different departments. There is a lack of skilled resources and the company experiences financial issues. Senior management does not address the prioritization of projects. Which of the following risk categories should the project manager consider when developing the risk management plan? A.Project management B.Technical C.External D.organizational 項目的各項活動之前存在復雜的依賴關(guān)系。這些活動被分配給不同部門的資源。公司缺乏經(jīng)驗豐富的資源,且公司經(jīng)歷財務問題。高級管理層沒有解決項目的優(yōu)先問題。制定風險管理計劃時,項目經(jīng)理應該考慮下列哪一項風險類別? A.項目管理 B.技術(shù)類 C.外部類 D.組織類 PMP答案解析:組織類項目風險:項目依賴關(guān)系、資源、資金、優(yōu)先級。 PMP參考答案:D PMP考試練習題二 After a component supplier goes out of business, a project manager review the following alternatives.Alternative A requires and investment of US$30,000, with a 70 percent chance of compatibility with the current prototype and revenues of US$300,000. If the component provides only partial functionality, revenues would be US$160,000.Alternative B requires an investment of US$20,000, with a 60 percent chance of incompatibility with the current prototype and revenues of USI120,000. If solution B fully works, revenus could be US$400,000.What is the expected monetary value (EMV) of the best alternative? A. US$189,000 B. US$212,000 C. US$228,000 D. US$270,000 在一個部件供應商倒閉后,項目經(jīng)理審查了以下可選方案:方案A要求投資30,000美元,與當前原型有70%的兼容機會,會產(chǎn)生300,000美元的收入。如果部件僅提供部分功能,則收入將為160,000美元。方案B要求投資20,000美元,與當前原型有60%的不兼容機會,會產(chǎn)生120,000美元的收入;如果方案B完全可行的話,收入可能達到400,000美元。那么最佳可選方案的預期貨幣價值(EMV)是多少? A.189,000美元 B.212,000美元 C.228,000美元 D.270,000美元 PMP答案解析:方案A:70%*300000+30%*160000-30000=228000 ,方案B:60%*120000+400000*40%-20000=212000 PMP參考答案:C |