PMP考試每天一練-2020年P(guān)MP考試練習(xí)題105
PMP考試練習(xí)題一: During a routine project update, the project sponsor stakes that the project schedule is unacceptably long. The project manager agrees to provide a proposal to accelerate the schedule.This is an example of which of the following? A.PUSH COMMUNICATION B.INTERACTIVE COMMUNICATION C.Success modeling D.Timeline adjustment 在一次例行項(xiàng)目更新中,項(xiàng)目發(fā)起人稱項(xiàng)目進(jìn)度時(shí)間之長(zhǎng)不可接受。項(xiàng)目經(jīng)理同意提供一份加快該進(jìn)度計(jì)劃的建議書。這屬于下列哪一項(xiàng)的實(shí)例? A.推式溝通 B.交互式溝通 C.成功模型 D.時(shí)間線調(diào)整 PMP答案解析:有來有去,交互式溝通。 PMP參考答案:B PMP考試練習(xí)題二 While working with the project team to prepare a network diagram, the project manager notices a series of activities can be performed in parallel, but must be finished in a specific sequence.What activity sequencing method is required? A, Operational diagramming method B. Precedence diagramming method C. Critical path method D. Arrow diagramming method 與項(xiàng)目團(tuán)隊(duì)一起合作制作一份網(wǎng)絡(luò)圖的時(shí)候,項(xiàng)目經(jīng)理注意到一系列活動(dòng)能夠并行執(zhí)行,且必須按特定順序完成。這需要哪一種活動(dòng)排序方法? A.操作繪圖法 B.緊前關(guān)系繪圖法 C.關(guān)鍵路徑法 D.箭頭繪圖法 PMP答案解析:排列活動(dòng)順序的工具,緊前關(guān)系繪圖法PDM。 PMP參考答案:B |