PMP考試每天一練-2020年PMP考試練習題107
PMP考試練習題一: Based on above chart, is this project in trouble with its budget? A.It is not possible to tell without similar information about completion progress B.It is not possible to tell without similar information about budget compliance C.It is not possible to tell without similar information about project risk register D.It is not possible to tell without similar information about quality performance 根據以上圖表所示,項目預算是否有問題? A.缺乏類似完成進度的相關信息,無法得知 B.缺乏類似預算相符水平的相關信息,無法得知 C.缺乏類似項目風險登記冊的相關信息,無法得知 D.缺乏類似質量績效的相關信息,無法得知 PMP答案解析:只有PV 和AC,沒有EV,很難確定信息。 PMP參考答案:B PMP考試練習題二 Activity 1 of project A has an external dependency (finish-to-start) from activity 2 of project B. The external dependency was identified as a schedule delay risk for project IL However, the project manager accepts the risk, which causes a delay. After acceptin8 this risks, what should the project manager have done to minimize the impact? A. Communicated the existence of the risk to the sponsor B. Coordinated both projects within a program C. Determined a contingency reserve D. Established a management reserve 項目A的活動1有一個來自項目B活動2的外部依賴關系(結束到開始)。這個外部依賴關系被識別為項目真的一個進度延期風險。然而,項目經理接受風險,并導致延期。接受這個風險之后,項目經理應該完成哪項工作來盡可能降低影響? A.與項目發起人溝通風險的存在 B在一個項目群中協調兩個項目 C.確定應急儲備 D.建立管理儲備 PMP答案解析:主動接受風險的應對措施是建立應急儲備。 PMP參考答案:C |