PMP考試每天一練-2020年P(guān)MP考試練習(xí)題110
PMP考試練習(xí)題一: During the implementation of an information technology(IT) development project, severe weather conditions in country X prevent developers from travelling to the IT company’s offices. To minimize the impact of this risk, the project manager transfers the work to another software development team based in country Y.The project manager’s actions are an example of which risk response strategy? A.Risk mitigation B.Risk transference C.Management reserve allocation D.Contingency response 在執(zhí)行一個信息技術(shù)(IT)開發(fā)項目過程中,X國惡劣的天氣情況讓開發(fā)人員不能前往IT公司的辦公室。為了盡可能減少該風(fēng)險的影響,項目經(jīng)理將工作轉(zhuǎn)移給Y國的另一個軟件開發(fā)團隊。項目經(jīng)理的行動屬于哪一種風(fēng)險應(yīng)對策略的范例? A.風(fēng)險減輕 B.風(fēng)險轉(zhuǎn)移 C.管理儲備分配 D.應(yīng)急應(yīng)對 PMP考試答案解析:題干說為了盡可能“減少”該風(fēng)險的影響,PM將工作轉(zhuǎn)移給Y國的另一個軟件開發(fā)團隊。這是減輕風(fēng)險影響,選用更可靠的供應(yīng)商。 PMP考試參考答案:A PMP考試練習(xí)題二 During the approval of a project management plan, the project sponsor identifies an external risk overlooked by the project team. What should the project manager do? A. Plan the risk response B. Identify risk and mitigation activities C. Add the risk to the risk register and ask the project team to review the project management plan to consider ist significance D. Ask the project sponsor to submit a formal change request and present to other stakeholders. 在批準項目管理計劃期間,項目發(fā)起人識別到一個被項目團隊忽略的外部風(fēng)險。項目經(jīng)理應(yīng)該怎么做? A.制定風(fēng)險應(yīng)對計劃 B.識別風(fēng)險和風(fēng)險減輕活動 C.將風(fēng)險添加進風(fēng)險登記冊,并要求項目團隊審查項目管理計劃,考慮該風(fēng)險的重要性 D.要求項目發(fā)起人提交一份正式的變更請求,并提供給其他項目干系人 PMP考試答案解析:識別到新風(fēng)險后,首先應(yīng)該更新進風(fēng)險登記冊。 PMP考試參考答案:C |