PMP考試每天一練-2020年PMP考試練習題111
PMP考試練習題一: During the project’s system testing phase, the testing team discovers the reoccurrence of many defects that were previously closed. What should the project manager do next? A.Ask the technical lead why the defect rate suddenly increased B.Verify that the testing team is using the proper testing methodology C.Analyze the reasons for the high defect rate with the assistance of the testing teams D.Submit a change request to eliminate the defects 在項目的系統測試階段,測試團隊發現之前已關閉的許多缺陷再次發生。項目經理下一步該怎么做? A.詢問技術主管缺陷率突然上升的原因 B.確認測試團隊使用的是正確的測試方法 C.在測試團隊的協助之下,分析發生高缺陷率的原因 D.提交變更請求減少缺陷 PMP考試答案解析:缺陷再次發生,應該去分析原因。 PMP考試參考答案:C PMP考試練習題二 During project execution, the sponsor leaves the company. What should the project manager do next? A. Perform integrated change control B. Decentralize project authority and decision-making C. Produce a project status report D. Conduct a stakeholder analysis 在項目執行期間,項目發起人離開公司。項目經理接下來應該怎么做? A.執行整體變更控制 B.分散項目權利和決策制定。 C.制作一份項目狀態報告。 D.進行干系人分析。 PMP考試答案解析:發起人離開公司,對項目的影響很大。通過對干系人進行分析,識別出干系人的利益、期望和影響。 PMP考試參考答案:D |