PMP考試每天一練-2020年P(guān)MP考試練習(xí)題116
PMP考試練習(xí)題一: Five projects are planned to be completed within a year under the authority of one sponsor. A functional manager, who owns the project resources, begins to implement all five projects according to the sponsor’s request. However, the project manager believes all five projects cannot be completed due to limited resources and budget What should the project manager do during the initiating phase to document this concern? A.Perform cost and time analysis to determine if five projects can be completed within the year B.Document the concern as a high-level risk and a constraint for each of the five projects C.Follow the sponsor’s request D.Withdraw from the project 五個(gè)項(xiàng)目在一名發(fā)起人的授權(quán)之下,計(jì)劃在一年內(nèi)完成。一名擁有項(xiàng)目資源的職能經(jīng)理開始按照發(fā)起人的要求執(zhí)行所有五個(gè)項(xiàng)目。但是,項(xiàng)目經(jīng)理卻認(rèn)為由于資源和預(yù)算有限無(wú)法完成所有五個(gè)項(xiàng)目。項(xiàng)目經(jīng)理應(yīng)在啟動(dòng)階段怎么做來(lái)記錄該問題? A.執(zhí)行成本和時(shí)間分析,確定五個(gè)項(xiàng)目是否能夠在一年內(nèi)完成 B.將該問題記錄為所有五個(gè)項(xiàng)目共有的高級(jí)風(fēng)險(xiǎn)和制約因素 C.遵循發(fā)起人的要求 D.退出該項(xiàng)目 PMP考試答案解析:在啟動(dòng)階段,項(xiàng)目經(jīng)理參與制定項(xiàng)目章程,將該問題記錄為所有五個(gè)項(xiàng)目共有的高級(jí)風(fēng)險(xiǎn)和制約因素,提交討論、備案。 PMP考試參考答案:B PMP考試練習(xí)題二 A project is cancelled due to a quality ad scheduling issues. In addition, a competitor just released a similar product; the project manager is assigned to a new project with a fixed deadline.What should the project manager do to ensure that to same issue does not occur again? A. Conduct performance review and apply corrective actions. B. Use the information provided in the final reports of previous projects. C. Apply rolling wave planning to the work breakdown structure. D. Assign subject matter experts t tasks on the critical path, 一個(gè)項(xiàng)目由于質(zhì)量和進(jìn)度問題被取消了。此外,競(jìng)爭(zhēng)對(duì)手剛剛發(fā)布了一個(gè)類似產(chǎn)品。項(xiàng)目經(jīng)理被分配管理一個(gè)具有固定期限要求的新項(xiàng)目。項(xiàng)目經(jīng)理應(yīng)該怎么做,來(lái)確保不會(huì)再次發(fā)生同樣的向題? A.開展績(jī)效審查,并應(yīng)用糾正措施。 B.使用之前項(xiàng)目最終報(bào)告中提供的信息。 C.對(duì)工作分解結(jié)構(gòu)應(yīng)用滾動(dòng)式規(guī)劃。 D.將主題專家分配到處于關(guān)鍵路徑上的任務(wù)。 PMP考試答案解析:參考之前項(xiàng)目的歷史信息。 PMP考試參考答案:B |