PMP考試每天一練-2020年PMP考試練習題117
PMP考試練習題一: Since the project schedule does not meet the time constraints, the project manager outsources the most difficult task to a provider known to be competent, bue expensive. The provider’s contract is a cost-plus-fixed-fee.Which of the following documents should the project manager update? A.Schedule and cost management plans B.Cost, risk, schedule, and communications management plans C.Risk, procurement, and schedule management plans D.Schedule, cost, risk, communications, and procurement management plans 因為項目進度不滿足時間制約因素,項目經理將最困難的任務外包給一個知道其有能力但昂貴的供應商。該提供商的合同是成本加固定費用合同。項目經理應更新下列那一份文件? A.進度和成本管理計劃 B.成本、風險、進度和溝通管理計劃 C.風險、采購和進度管理計劃 D.進度、成本、風險、溝通和采購管理計劃 PMP考試答案解析:實施采購的輸出,項目管理計劃更新。見PMBOK。 PMP考試參考答案:D PMP考試練習題二 A new project manager reviews a project's documentation, information, and data. Concerned about project delays, the new project manager wants to identify relationships between the variables.What tool should the project manager use to determine if changes should be made to the project? A. Ishikawa diagram B. Control chart C. Histogram D. Scatter diagram 一名新項目經理審查了項目的文檔,信息和數據。因為擔心項目延遲,新項目經理希望識別變量之間的關系。項目經理應該使用什么工具來確定是否應該對項目進行變更? A.石川圖 B.控制圖 C.直方圖 D.散點圖 PMP考試答案解析:散點圖可確定變量之間的關系。 PMP考試參考答案:D |