PMP考試每天一練-2020年PMP考試練習題119
PMP考試練習題一: A new project manager compiles the stakeholder register for a project to automate the audit management process and to review previous projects’records. The project manager should use which of the following as a reference for the stakeholder register? A.Cross-functional flowchart that shows all steps in the audit management process B.Communications management plans within previous projects’ records C.Detailed charter of the new project D.Customer survey data for the audit management process 為自動化審計管理流程以及審查之前項目的記錄,新項目經理編制干系人登記冊。項目經理應該使用下列哪一項作為干系人登記冊的參考? A.顯示審計管理流程所有步驟的多職能流程圖 B.之前項目記錄中的溝通管理計劃 C.新項目的詳細章程 D.審計管理流程的客戶調查數據 PMP考試答案解析:制定干系人登記冊(識別干系人的輸出),需要參考項目章程(識別干系人的輸入)。 PMP考試參考答案:C PMP考試練習題二 After delivering a new computer, application to an external customer, the customer asks for supplemental system documentation. What should the project manager do first? A. Check if contingency reserves are sufficient for the change. B. Update the project budget and schedule to include the change C. Ask the customer to submit a change request. D. Ask the project team to provide the requested documentation. 向外部客戶交付新計算機應用程序后,客戶要求補充系統文檔。項目經理首先應該做什么? A.檢查應急儲備是否足以進行變更 B.更新項目預算和進度計劃包含變更 C.要求客戶提交變更請求 D.要求項目團隊提供請求的文檔 PMP考試答案解析:首先應該讓客戶提交變更請求。 PMP考試參考答案:C |