PMP考試每天一練-2020年P(guān)MP考試練習(xí)題133
PMP考試練習(xí)題一: A chief information officer informs the project manager that using a common file-sharing website for projects violates the company’s security requirements. In which of the following documents should the project manager have found this requirement included? A.Project security plan B.Organizational process assets C.Enterprise environmental factors D.Project management information system 首席信息官告知項(xiàng)目經(jīng)理項(xiàng)目使用一個(gè)公共文件共享網(wǎng)站的行為違反了公司的安全要求。項(xiàng)目經(jīng)理應(yīng)在下列那一份文件中找到這項(xiàng)需求? A.項(xiàng)目安全計(jì)劃 B.組織過(guò)程資產(chǎn) C.事業(yè)環(huán)境因素 D.項(xiàng)目管理信息系統(tǒng) PMP考試答案解析:PMBO原話:特定的組織標(biāo)準(zhǔn),例如政策(如人力資源政策、健康與安全政策)屬于組織過(guò)程資產(chǎn)。 PMP考試參考答案:B PMP考試練習(xí)題二 According to company standards, a web page should load within four seconds. The testing team concludes that a specific webpage loads between six to eight seconds. What should the project manager do first? A. Initiate a change request for an exception to the standard. B. Perform an assessment regarding how the test was conducted. C. Work with the team to determine the root cause of the issue D. Evaluate the impact of non-compliance with a risk matrix. 按照公司標(biāo)惟,網(wǎng)頁(yè)必須在四秒鐘內(nèi)加載完成。測(cè)試團(tuán)隊(duì)發(fā)現(xiàn)某個(gè)網(wǎng)頁(yè)的加載時(shí)間是六到八秒鐘。項(xiàng)目經(jīng)理首先應(yīng)該怎么做? A.為這個(gè)標(biāo)準(zhǔn)例外情況提出變更請(qǐng)求。 B.執(zhí)行有關(guān)如何開(kāi)展測(cè)試方面的評(píng)估。 C.與團(tuán)隊(duì)合作,確定問(wèn)題的根本原因。 D.評(píng)價(jià)風(fēng)險(xiǎn)矩陣不符合項(xiàng)的影響。 PMP考試答案解析:調(diào)查事情的根本原因。 PMP考試參考答案:C |