PMP考試每天一練-2020年PMP考試練習題159
PMP考試練習題一: A project manager creates the work breakdown structure (WBS) and WBS dictionary. What factor should be used to determine the level of detail of the work package? A. Top-down approach B. Complexity of the project C. Form of the WBS structure D. Individual work component 項目經理創建了工作分解結構(WBS)和WBS詞典。應該使用下列哪一個因素來確定工作包詳情和層次? A. 自上而下法 B. 項目的復雜性 C. WBS結構的格式 D. 單個的工作組成部分 PMP考試答案解析:工作包的詳細程度因項目的大小與復雜程度而異。 PMP考試參考答案:B PMP考試練習題二 During a project status meeting, the project manager reviews with the team several risk areas and suggests a mitigation plan for each risk area. A team member suggests a different mitigation strategy for two risks. The project manager reviews all options with the project team. Which of the following modes of conflict resolution does the project manager use? A, Collaboration/Problem Solve B. Withdrawal/Avoid C. Compromise/Reconcile D. Force/Direct 在項目狀態會上,項目經理與團隊一起審查多個風險領域,并為每個風險領域建議一個減輕計劃。一名團隊成員為兩個風險建議了一種不同的風險減輕策略。項目經理與項目團隊一起審查所有方案。項目經理使用的是下列哪一種沖突解決模式? A.合作/解決問題 B.撤退/回避 C.妥協/調解 D.強迫/命令 PMP考試答案解析:項目經理與項目團隊一起審查所有方案,這是合作/解決問題。 PMP考試參考答案:A |