PMP考試每天一練-2020年PMP考試練習題160
PMP考試練習題一: A project manager is assigned to a project and is organizing group activities to document the requirements baseline for that project. What are the group creativity techniques that can be used? A. Brainstorming and affinity diagrams B. Unanimity and plurality C. Proto typers and requirements documentation D. Benchmarking and control charts 某項目經理受命承擔一個項目,并且目前通過團體活動制定該項目的需求基準。可采用何種團體活動方法? A. 頭腦風暴法和親和圖法 B. 一致同意和大多數原則 C. 原型和需求文件 D. 基準和控制圖 PMP考試答案解析:選項A和B都是團體活動,但是看英文能夠發現題目問的是group creativity techniques團體創新技術。 PMP考試參考答案:A PMP考試練習題二 The development team observes that two major project variables are moving in opposing directions, which could put the project at risk. What tour technique should the project manager use to determine how closely related these two variables are? A. Scatter diagram B. pare to chart C. Histogram D. Variance analysis 開發團隊觀察到兩個主要項目變量向相反方向移動,可能導致項目處于風險當中。項目經理應使用什么工具或技術來確定這兩個變量是如何密切相關的? A.散點圖 B.帕累托圖 C.直方圖 D.偏差分析 PMP考試答案解析:確定兩個變量之間的關系使用散點圖。 PMP考試參考答案:A |