PMP考試每天一練-2020年PMP考試練習題161
PMP考試練習題一: While conducting a project audit, the program manager finds all the items in the issue log are owned by the project manager.Is this acceptable? A. No,the project manager cannot be the owner of issues and their resolution B. No,the project team must be the responsible owner of all issues and their resolution C. Yes,it is required that all issues have an assigned owner D. Yes,the project manager must be the owner of all issues and their resolution 項目群經理在實施項目審計時,發現問題日志中各項均為項目經理所有。該情況可否接受? A. 不可接受,項目經理不得作為問題及其解決方案的所有者 B. 不可接受,項目團隊必須是所有問題及其解決方案的負責任的所有者 C. 可接受,根據要求,所有問題均有指定的所有者 D. 可接受,項目經理必須是所有問題及其解決方案的所有者 PMP考試答案解析:首先排除A和D。選項C從邏輯上來看并沒有錯,但是不符合PMI的理念,做項目講究團隊合作,PM不可能所有問題都是自己負責。 PMP考試參考答案:B PMP考試練習題二 A stakeholder states that they did not receive the root cause analysis regarding an issue raised during a recent project status meeting. The project manager discovers that the stakeholder is not included in the report distribution list. What should the project manager do first? A. Reference the risk register. B. Update the communications management plan. C. Perform a change request. D. Update the stakeholder register. 一名干系人表示未收到近期項目狀態會議上提出的某個問題的根本原因分析,項目經理發現該干系人沒有包含在報告分發名單中。項目經理首先應該怎么做? A.參考風險登記冊。 B.更新溝通管理計劃 C.執行變更請求。 D.更新干系人登記冊。 PMP考試答案解析:未收到信息,這是溝通出了問題。 PMP考試參考答案:B |