PMP考試每天一練-2020年P(guān)MP考試練習題162
PMP考試練習題一: Which of the following is the process of improving the competencies, team interaction, and the overall team environment to enhance project performance? A. Manage Project Team B. Acquire Project Team C. Select Project Team D. Develop Project Team 下列哪一過程可促進能力素質(zhì)、團隊互動以及提升項目績效的整體團隊環(huán)境? A. 管理項目團隊 B. 組建項目團隊 C. 選擇項目團隊 D. 建設(shè)項目團隊 PMP考試答案解析:建設(shè)項目團隊可以促進個人能力提高、團隊互動、提升項目績效。 PMP考試參考答案:D PMP考試練習題二 The project’s earned value reports the cost performance index is 0.87, and the schedule performance index is 1.18. What does the report indicate to the program manager regarding the project? A. Ahead of schedule and over budget B. Ahead of schedule and under budget C. Behind schedule and under budget D. Behind schedule and over budget 項目的掙值報告成本績效指數(shù)為0.87,而進度績效指數(shù)為1.18。這份報告對項目群經(jīng)理說明了項目處于什么狀態(tài)? A.超前于進度,但超出預(yù)算 B.超前于進度:并低于預(yù)算 C.落后于進度,但低于預(yù)算 D.落后于進度,并超出預(yù)算 PMP考試答案解析:成本超支、進度提前。 PMP考試參考答案:A |