PMP考試每天一練-2020年PMP考試練習題178
PMP考試練習題一: While preparing for a project, a project management considers how to deal with large changes that may occur during project execution, the project manager should do which of the following? A. Discuss all changes with the project sponsor as soon as they are requested. B. Express in the project management plan that the large changes cannot be accommodated. C. Ensure that a change control board is established to deal with such situations if they occur. D, Inform the project team that all changes must be approved by the project manager. 準備項目時,項目經理考慮如何處理在項目執行過程中可能發生的重大變更。項目經理應采取下列哪一項措施? A.在項目發起人請求變更時立即與他們討論所有變更 B.在項目管理計劃中明確表示不允許有重大變更 C.確保建立變更控制委員會,在發生這種情況時立即處理 D.通知項目團隊,所有變更都必須由項目經理批準 PMP考試答案解析:重大變更應該確保獲得變更控制委員會的批準。 PMP考試參考答案:C PMP考試練習題二 一個項目由三個活動組成。A活動歷時5周,B活動歷時6周,C活動歷時7周。活動排序為A-B-C。但是,活動B的資源分配要1周,C在B活動開始1周后開始。則該項目最短工期是多少? A:12 周 B:13 周 C:14 周 D:16 周 PMP考試答案解析:指南-6.3.2.2 確定和整合依賴關系&6.3.2.3 提前量和滯后量,如圖:5+7+2=14 PMP考試參考答案:C |