PMP考試每天一練-2022年P(guān)MP考試模擬題91
PMP考試練習(xí)題一: 在項(xiàng)目施工階段,供應(yīng)商處發(fā)生火災(zāi),導(dǎo)致原材料的供應(yīng)延遲了一周,項(xiàng)目經(jīng)理已識別到延遲的風(fēng)險(xiǎn)并包含在計(jì)劃當(dāng)中,發(fā)生這個(gè)事件之后,項(xiàng)目經(jīng)理首先應(yīng)該怎么做? During the project's construction phase, a supplier has a fire and the supply of raw material is delayed by a week, The project manager identified the risk of a delay and inclued it in the plan .After the occurrence of the event, what should the project manager do first? A:執(zhí)行風(fēng)險(xiǎn)響應(yīng)計(jì)劃 Carry out risk response planning B:由于材料延誤,要求項(xiàng)目延期 Ask for an extension of the project due to delay C:更新項(xiàng)目基準(zhǔn) Update the project baseline D:更新風(fēng)險(xiǎn)登記冊 Update the risk register PMP考試答案解析:所屬知識領(lǐng)域:項(xiàng)目風(fēng)險(xiǎn)管理。所屬過程組:監(jiān)控過程組。項(xiàng)目經(jīng)理已經(jīng)識別了延誤的風(fēng)險(xiǎn),并將該風(fēng)險(xiǎn)應(yīng)對納入了計(jì)劃,當(dāng)該風(fēng)險(xiǎn)發(fā)生時(shí)執(zhí)行風(fēng)險(xiǎn)應(yīng)對計(jì)劃即可,監(jiān)控風(fēng)險(xiǎn)包括實(shí)施風(fēng)險(xiǎn)應(yīng)對計(jì)劃,B不符合題意,C該風(fēng)險(xiǎn)的應(yīng)對措施已經(jīng)納入計(jì)劃,當(dāng)該風(fēng)險(xiǎn)發(fā)生時(shí)無需更當(dāng)該風(fēng)險(xiǎn)發(fā)生時(shí)無需更新基準(zhǔn),D風(fēng)險(xiǎn)登記冊中已包括該風(fēng)險(xiǎn),無需更新風(fēng)險(xiǎn)登記冊。考點(diǎn):監(jiān)督風(fēng)險(xiǎn)。出處:PMBOK第6版 中 11.7。 PMP考試參考答案:A PMP考試練習(xí)題二: 關(guān)于運(yùn)營相關(guān)方的描述不正確的是: A. 運(yùn)營相關(guān)方應(yīng)該參與項(xiàng)目。 B. 需求要記錄在相關(guān)方登記冊中。 C. 為了促進(jìn)運(yùn)營相關(guān)方有效參與決策,應(yīng)規(guī)劃管理策略。 D. 無需考慮他們對項(xiàng)目的參與。 PMP考試參考答案:D |