PMP考試每天一練-2023年P(guān)MP考試模擬題16
PMP考試練習(xí)題一: 項(xiàng)目經(jīng)理與主題專家(SME)一起估算項(xiàng)目任務(wù)。主題專家認(rèn)為某項(xiàng)活動(dòng)最可能花45小時(shí)完成。但是,在項(xiàng)目團(tuán)隊(duì)會(huì)議上,相同的活動(dòng)估計(jì)需要花70小時(shí)。而有些團(tuán)隊(duì)成員認(rèn)為這項(xiàng)活動(dòng)能夠在32小時(shí)內(nèi)完成。 項(xiàng)目經(jīng)理應(yīng)該怎么估算這項(xiàng)活動(dòng)? The project manager estimates project tasks with subject matter experts (SMEs). The SMEs feel that an activity will most likely take 45 hours to complete. However, during a project team meeting, the same activity is estimated to take 70 hours. Some team members believe that this activity can be completed within 32 hours. What should the project manager estimate for this activity? A、32小時(shí) 32 hours B、45小時(shí) 45 hours C、47小時(shí) 47 hours D、70小時(shí) 70 hours PMP考試答案解析:三點(diǎn)估算的公式 PMP考試參考答案:C PMP考試練習(xí)題二: 下面關(guān)于進(jìn)度數(shù)據(jù)的說法,錯(cuò)誤的是: A、進(jìn)度數(shù)據(jù)至少應(yīng)包括進(jìn)度里程碑、計(jì)劃活動(dòng)、活動(dòng)屬性以及已知的全部假設(shè)條件與制約因素。 B、在進(jìn)度模型中,把進(jìn)度計(jì)劃看成是自變量,進(jìn)度數(shù)據(jù)是因變量。 C、進(jìn)度數(shù)據(jù)可以包括資源直方圖、現(xiàn)金流量預(yù)測以及訂貨與交貨進(jìn)度計(jì)劃等。 D、有了進(jìn)度數(shù)據(jù)和進(jìn)度模型,就可以很方便地更新項(xiàng)目進(jìn)度計(jì)劃。 PMP考試參考答案:B |