PMP考試練習(xí)題一: 在項(xiàng)目評(píng)審會(huì)上,從事活動(dòng) AD 的項(xiàng)目團(tuán)隊(duì)成員通知項(xiàng)目經(jīng)理,完成該活動(dòng)還需要三天,組織的高級(jí)經(jīng)理要求項(xiàng)目經(jīng)理,即使需要額外的預(yù)算,也必須找到方法,按原定基準(zhǔn)計(jì)劃支付項(xiàng)目。項(xiàng)目應(yīng)該使用什么方法來(lái)滿足高級(jí)經(jīng)理的需求? During a project review meeting, the project team member working on activity AD advises the project manager that it will take three more days to complete the activity. The organization's senior manager asks the project manager to find ways to deliver the project according to the original baseline plan, even though it may need additional budget. What should the project manager use to meet the senior manager's needs? A:使用快速跟進(jìn) Use fast tracking B:使用趕工 Use fast crashing C:應(yīng)用關(guān)鍵鏈法 Apply critical chain method D:應(yīng)用時(shí)間提前量和時(shí)間滯后量 Apply leads and lags PMP考試答案解析:指南-6.5.2.6進(jìn)度壓縮,趕工。題中提到了“額外的預(yù)算”,即多花錢是可以的,一般表現(xiàn)為加班,加人,達(dá)到趕工的目的。 PMP考試參考答案:B PMP考試練習(xí)題二: 控制成本過(guò)程的輸出包括: A. 成本概算 B. 成本預(yù)算 C. 成本基準(zhǔn) D. 成本預(yù)測(cè) PMP考試參考答案:D |